The development application for the Manly State Boat Harbour redevelopment has moved into a detailed information request phase, with planning assessors identifying ten areas requiring further information or revised plans before assessment can progress.
The information request, issued on 6 March 2026, is a standard and necessary step in the assessment process. It does not signal a refusal. The applicant, MA Marina Fund TT Pty Ltd acting through Willowtree Planning, has until approximately 6 June 2026 to respond before the assessment clock resumes.
Ten Questions Assessors Need Answered
The most pointed questions go to the scale of the proposed upper-floor bistro. Assessors flagged that it is substantial in both floor area and expected patron numbers, and that the application does not sufficiently demonstrate how it remains subordinate to and directly associated with the ground-floor club use rather than operating as a standalone restaurant.

The applicant must either prove that link with specific details on intended operators, expected patronage and access restrictions, or seek a separate development permit for the bistro in its own right.
The five proposed retail tenancies raised a similar flag, with assessors requiring the applicant to show the shops would be associated with marina activities and would not undermine the viability of the nearby Manly Harbour Village centre.
On parking, assessors found the proposed reduction from 148 to 118 spaces insufficiently justified. The applicant must now conduct a peak hour traffic survey establishing existing trip generation, produce a net increase table showing the additional burden on the local road network, and clarify how many berths and facilities currently depend on the existing parking areas.

Other information requests cover noise and air quality from marine industry workshops, given the site sits within 100 metres of sensitive residential zoning across Royal Esplanade. The applicant must detail all industrial activities proposed including fibreglassing, grinding, spray painting and engine repair, and clarify the intended hours of operation for all uses.
Stormwater management, refuse vehicle access, landscaping, pedestrian connectivity to the streetscape and the existing Environmentally Relevant Activity approval on the site were also flagged as requiring further detail.
Energex Cleared the Application
One referral agency response has already come back positively. Energex assessed the application on 4 March 2026 and approved it in full, subject to conditions. The electrical network referral was triggered because the site sits within 100 metres of a supply infrastructure easement.
Energex confirmed the proposed works do not adversely affect the safe or efficient operation of the electricity network, with conditions requiring that no buildings or structures be placed within two existing underground cable easements on the site.
Residents Raise Concerns
Both public submissions received, lodged on 20 February 2026, home in on the same issue: parking.

Manly resident Andrew Wernbacher supports the development in principle but is firm on one point: the existing parking is already overwhelmed on weekends and holidays, with overflow regularly spilling onto local streets and into the nearby public boat ramp facility.
“I’m concerned that the reduction in proposed on-site parking will add excessive strain on the already overloaded local streets and adjoining public boat ramp facility,” Wernbacher wrote. “On-site parking needs to be increased, not decreased.”
The second submission, lodged with personal details removed at the submitter’s request, is an outright objection on the same grounds: “I oppose the proposed development solely on the grounds that this facility needs more parking not less. I will oppose the development unless the parking supply is increased and not decreased.”
The assessor’s requirement for a peak hour traffic survey and net increase analysis will now put hard data behind what both submitters are describing from lived experience.
What Happens Next
Once the applicant responds to the information request, assessment continues toward a formal decision by BCC. Residents can track the DA’s progress, view all documents and lodge a submission by clicking here.
Published 25-April-2026